The correct answer is B.

OBJ-7.1: Normal changes must be assessed, authorized, and scheduled prior to implementing the change. Standard changes are pre-authorized and therefore, don’t need to be scheduled since they are low-risk. Emergency changes still require an assessment and authorization, but they are rarely scheduled since they need to be implemented as soon as possible to fix an incident or security issue.