Show Answer

 

The correct answer is C.

OBJ-3.4: PRINCE2 Agile is built upon the concept of flexing or prioritizing what is delivered. In terms of progress reporting the project board should expect there to be more emphasis placed on the amount being delivered.

Hide Answer