The correct answer is C.

OBJ-3.3: When using PRINCE2 in an agile context it is important to plan around features and groups of features. Due to the primary focus of agile being based on flexing what is being delivered (see Chapter 6) features expressed in the form of requirements or user stories represent the contingency on a project when combining PRINCE2 with agile. Conversely, time and cost are not used as contingency and are therefore likely to remain stable.