Show Answer
The correct answer is D.
OBJ-3.6: Cost tolerance is fixed at zero tolerance for extra time on all levels of the plan.
Hide Answer
Show Answer
The correct answer is D.
OBJ-3.6: Cost tolerance is fixed at zero tolerance for extra time on all levels of the plan.