Show Answer

 

The correct answer is A.

OBJ-2.2: Tailoring is concerned with the appropriate use of PRINCE2 on any given project, ensuring that there is the right amount of governance, planning, and control, in accordance with PRINCE2’s principles. Processes may be combined or adapted (e.g. by adding or combining activities).

Hide Answer