The correct answer is B.

OBJ-3.4.3: PRINCE2’s recommended approach to product-based planning includes analyzing risks to a plan, designing a plan, defining and analyzing the products, identifying activities and dependencies, preparing estimates, preparing a schedule, and documenting a plan.