Show Answer

 

The correct answer is C.

OBJ-3.7.1: An exception report is produced when a stage plan or project plan is forecast to exceed tolerance levels set. It includes a description of the exception, its impact, options, recommendation, and impact of the recommendation. This report is prepared by the project manager for the project board.

Hide Answer