Show Answer

 

The correct answer is D.

OBJ-3.4.1: Exception plans must be produced to show the actions required to recover from or avoid a forecast deviation from agreed tolerances in the project plan or stage plan. For an exception at the stage level, it covers the period from the present to the end of the current management stage. If the exception is at the project level, the project plan will be replaced.