The correct answer is C.

OBJ-3.5.3: The risk actionee is an individual assigned to carry out a risk response action, taking direction from the risk owner. A risk owner is responsible for the management, monitoring, and control of all aspects of a particular risk allocated to them. Project assurance reviews risk management practices to check that they are in line with the risk management approach. Project support assists the project manager in maintaining the risk register.