Show Answer

 

The correct answer is B.

OBJ-3.4.2: To meet the requirements of PRINCE2, at a minimum a project must produce a stage plan for each management stage. A project plan is produced for the project as a whole, not for each management stage. A work package is an optional type of plan. An exception plan is only created if a tolerance is breached and an exception created.