Show Answer

 

The correct answer is A.

OBJ-1.2: The customer is responsible for delivering the benefits of the project. PRINCE2 is based on there being a customer/supplier environment. It assumes that there will be a customer who will specify the desired result and (usually) pay for the project. It also assumes the supplier will provide the resources and skills to deliver that result.

Hide Answer