The correct answer is B.

OBJ-4.1: An agreed project brief ensures that the project has a commonly understood and well-defined start point. A project brief is used to provide a full and firm foundation for the initiation of the project and is created in the starting up a project process. During the initiating a project process, the contents of the project brief are extended and refined in the PID, after which the project brief is no longer maintained.