The correct answer is D.

OBJ-4.2: The purpose of the closing a project process is to provide a fixed point at which acceptance for the project product is confirmed, and to recognize that objectives set out in the original project initiation documentation (PID) have been achieved. This means that the closing a project process provides an opportunity to ensure that all unachieved goals and objectives are identified so that they can be addressed in the future.