Show Answer
The correct answer is A.
OBJ-4.2: The starting up a project process only requests authorization to initiate a project. The purpose of the starting up a project process is to ensure that the prerequisites for initiating a project are in place by answering the question: Do we have a viable and worthwhile project? The decision to start the project must be explicit; the activities from starting up a project happen before this decision.