The correct answer is A.

OBJ-2.1: The manage by stages principles gives the project board the opportunity to assess the project’s viability at defined intervals. A PRINCE2 project is planned, monitored, and controlled, management stage by management stage. The project board delegates the authority for the day-to-day control of a management stage, within agreed tolerances, to the project manager.