The correct answer is D.

OBJ-2.1:/strong> Learning from experience takes place throughout PRINCE2: when starting a project, as the project progresses, and as the project closes. As the project closes, the project should pass on lessons by documenting them. These documented lessons are then used by other projects when they are starting up in order to provoke change. Unless lessons provoke change, they are only lessons identified (not learned).