Show Answer

 

The correct answer is A.

OBJ-3.7.3: A highlight report is a time-driven control, produced at a predefined frequency. The highlight report is a time-driven report from the project manager to the project board on management stage progress. A daily log is a useful tool for recording actions when reviewing progress, but it is not considered a PRINCE2 control.

Hide Answer