Show Answer

 

The correct answer is B.

OBJ-4.3: The managing product delivery process focuses on the acceptance, execution, and delivery of a work package. The purpose of the managing product delivery process is to control the link between the project manager and the team manager(s), by agreeing on the requirements for acceptance, execution, and delivery. The role of the team manager(s) is to coordinate an area of work that will deliver one or more of the project product’s components. They can be internal or external to the customer’s organization.

Hide Answer