Show Answer

 

The correct answer is D.

OBJ-2.1: A PRINCE2 project has defined tolerances for each project objective to establish limits of delegated authority. PRINCE2 enables appropriate governance by defining distinct responsibilities for directing, managing and delivering the project and clearly defining accountability at each level. These tolerances are set against the six aspects of performance (costs, time, quality, scope, benefits, and risks).

Hide Answer