Show Answer
The correct answer is C.
OBJ-4.1: The project controls are set up and established during the initiating a project process. The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.
Hide Answer