The correct answer is B.

OBJ-4.2: Subsequent stages are planned towards the end of each stage during the managing a stage boundary process. The purpose of the managing a stage boundary process is to enable the project manager to provide the project board with sufficient information to be able to review the success of the current management stage, approve the next stage plan, review the updated project plan, and confirm continued business justification and acceptability of the risks.