Show Answer

 

The correct answer is B.

OBJ-4.1: The controling a stage process covers the day-to-day activities of the project manager. The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.