Show Answer

 

The correct answer is C.

OBJ-4.1: The purpose of the managing a stage boundary process is to enable the project manager to provide the project board with sufficient information to be able to review the success of the current management stage, approve the next stage plan, review the updated project plan, confirm continued business justification and acceptability of the risks. Therefore, the process should be executed at, or close to, the end of each management stage.

Hide Answer