Show Answer

 

The correct answer is B.

OBJ-4.1: The purpose of the starting up a project process is to ensure that the prerequisites for initiating a project are in place by determining is a viable and worthwhile project exists. The decision to start the project must be explicit; the activities from starting up a project happen before this decision.

Hide Answer